Pipe3” Flex Pipe & 6” YJ Ground ConditionsClay, Cobble and Muskeg
Installation Length10138m ROW Width2m - 8m
Crossings14 Common Lines5

 Download Project Details

Cost Savings: Conventional Methods vs TPT

Project Summary

  • Gathering system and mainline installation complete utilizing Trenchless Pipeline Technologies
  • 5 lines in a common 8m ROW maintaining 1.5m cover in clay and cobble soils
  • Installation completed over 24 sections in 6 common entry and exit pits
  • All five pipelines were installed in separate holes maintaining 1 meter spacing
  • Field fit bends were utilized for steel line tie-ins as required

Work Area

  • 6 work areas of 15m x 40m were stripped and cleared
  • Existing access roads and cut lines were available for use to complete project
  • The ROW was not salvaged of timber, cleared or mulched for the execution of this project

By the Numbers

  • Scope: Gathering System – well sites and satellite installation
  • Duration: 14 days – not including testing
  • Work area & ROW Clearing and Salvage: approximately 3,600 sq. meters

Right of Way