Pipe3” Flex Pipe Ground ConditionsClay, Gravel, Sand & Muskeg
Installation Length4278m ROW Width5m
Crossings8 Common Lines4

 Download Project Details

Cost Savings: Conventional Methods vs TPT

Project Summary

  • Gathering system was completed utilizing Trenchless Pipeline Technologies
  • 4 lines in a common 5m ROW maintaining 1.5m cover in clay and muskeg
  • Installation was completed over 6 sections with 1 common entry and exit pit
  • All 4 pipelines were installed in separate holes maintaining 1 meter spacing

Work Area

  • 1 work area of 15m x 40m was salvaged of timber, stripped and cleared
  • Exit pits and pipe reels were set up at riser locations on lease
  • ROW was not salvaged of timber, cleared or mulched for the execution of this project
  • Swamp weights, rip rap or matting was not required.

By the Numbers

  • Scope: Gathering System – well sites and tie-in to existing satellites
  • Duration: 4 days – not including testing
  • Work Area & ROW Clearing and Salvage: approximately 600 sq. meters

Right of Way